Sand and gravel are the largest, indispensable and irreplaceable raw materials for infrastructure construction in my country, with an annual consumption of about 20 billion tons. It is the world's largest mineral resource, raw material and bulk commodity. With the release of relevant industrial policies and planning requirements, the future development trend of the sand and gravel industry is intelligent, green, high-quality, well-managed, efficient and large-scale. The sand and gravel industry has fully entered a new stage of high-quality development marked by green and low carbon. The green and low-carbon management system of China's sand and gravel industry with distinctive features of green mines, green factories, and green bases are rapidly being built.

The production investment cost of starting a sand and gravel factory involves all aspects. This article will analyze the production investment cost budget from the following aspects.

jaw crusher, cone crusher for river stone, Vanguard Machinery

1. prophase investment

(1). Document procedures

The production of sand and gravel plants involves the extraction of mineral resources. Therefore, the establishment of a sand and gravel plant must go through certification procedures such as environmental protection, industry and commerce, and mining licenses, mainly including the mining license of the land and resources department, the business license and tax registration of the industry and commerce department, as well as safety management and environmental protection bureau evaluation. Due to different policies in different regions, the time and cost required for certificate application procedures are also different. Users are advised to consult professional departments.

(2). Mine site

To open a sand and gravel plant, it is necessary to select a suitable mine site, either by purchasing a mine or leasing a production site. The mine site also requires a certain amount of capital investment, which can be negotiated with the mine owner or department according to the local market conditions.

2. Medium-term investment

(1). Purchase of sand and gravel equipment

The crushing production line of the stone plant is not only composed of a single piece of equipment, but also composed of feeders, crushing equipment, sand making equipment, vibrating screens, sand washing machines and belt conveyors. It is not same in the nature, finished product output size, site planning, etc. Different manufacturers have different equipment models, configurations, material selection, production output, etc., so the equipment investment costs in the market will also be slightly different.

(2). Civil construction

Generally speaking, each equipment of the sand and gravel plant, such as silos, crushers, vibrating screens, belt conveyors, etc., need to do corresponding infrastructure construction, and need to purchase materials such as concrete, steel bars, steel plates, steel formwork, etc. This part also needs certain budget.

(3). Environmental protection

The environmental protection aspect is particularly important. Many places require that the sand and gravel pits should undergo an environmental impact assessment before construction, and construction can only be done after approval by the environmental department. In terms of pollution prevention and control in the sand and gravel yard, there are waste water, dust, noise, solid waste, etc. The specific environmental protection measures include installing dust removal equipment at the main dust-raising points, sealing the production workshop, hardening the road in the factory area, and greening the surrounding environment.

3. Follow-up investment

The follow-up investment in the sand and gravel pits mainly includes equipment operating costs, water and electricity costs during production and operation, employee salaries (feeders, mechanics, electric control operators, etc.) and equipment material losses (crushing equipment wear-resistant materials and other equipment. consumption of wearing parts), etc., all of which require a certain amount of capital investment.

The above is the investment required to start a sand and gravel factory. The scale of the sand and gravel factory and the configuration plan of the production line are different, and the amount of investment will also be different. The total investment ranges from hundreds of thousands to tens of millions. It is recommended that users Before setting up a sand and gravel factory, fully understand the project, such as: procedures, site, capital, equipment, etc., inspect the factory on the spot, compare and consider carefully.